Christopher Park Construction Update

It is exciting to see the progress on the construction at George Christopher Park. It is awesome that the San Francisco Recreation and Park Department has included replacing the baseball fencing and resurfacing the tennis court in the renovations.

Laura Chavez Message on the Construction Progress:

Cheers George Christopher Community,

There has been tremendous progress on George Christopher Playground Renovation this summer. The irrigation mainline piping has been installed, the concrete and CMU walls around the plaza and ramp area are almost complete, and the new plaza has been poured. The new single stall ADA restroom is tiled and painted, and the planters around the play areas have been formed. A couple weeks ago, our contractor started digging footings for the play equipment, and as the pieces come together for layout, you can glimpse how awesome this playground is going to be.

There was little response when I emailed at the start of the pandemic to notify you that one of the Jim Miller-Melberg play sculptures was unfortunately damaged during the course of construction. We’ve been working with the contractor and several committed community members and are pleased to announce that a replacement sculpture will be made for the new sculpture play area. We’ve coordinated with our deferred maintenance team and will be replacing the fencing at the ball field and resurfacing the tennis court in parallel with the playground renovation. The project team has also worked with several city departments to strategize around park accessibility, and we are revising our pathway plans and site signage so folks of all abilities can better navigate to all park amenities.

Please reach out with any questions or concerns.

Best,

Lauren

Lauren Dietrich Chavez

Project Manager, Capital & Planning Division

We Have Moved! After August 5, 2020, you can reach me at:

San Francisco Recreation and Park Department  | City & County of San Francisco

49 South Van Ness Avenue, Suite 1220 | San Francisco, CA 94103

(628) 652-6643  |  lauren.chavez@sfgov.org


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s