NOTICE OF CONSTRUCTION
San Francisco Public Works will be performing the remediation of the failing pavement area on Diamond Heights Blvd. between Duncan St. and Clipper St. This work is urgent as the pavement has failed and needs to be repaired immediately.
WORK PLAN
We will be reconstructing a portion of the three lanes on the Diamond Heights Blvd. between Clipper Street and Duncan Street. At least one traffic lane will be provided at all times and no detours will be required. Parking will not be affected.
WORK SCHEDULE
Monday, July 30 through Wednesday, August 1, 2018
7am to 4pm
· Monday – reconstruct the two northern lanes
· Tuesday – reconstruct the remaining lane nearest the median.
· Wednesday – pave with 2” asphalt.
If you have questions, please feel free to contact me. Thank you.
Grace L. Moore
Public Affairs Officer
Office of Communications & Public Affairs
San Francisco Public Works
City and County of San Francisco
Ph (415) 558-5282 Fx (415) 522-7723