Please see the forwarded message from Dadisi Najib, Public Works, who is the Information Officer for all the work along Diamond Heights Blvd. The work is scheduled to start January 30th. If you have questions, please email Dadisi. Or join us for our DHCA Meeting on Feb. 7 at 7 pm at the SF Police Academy to hear about the project from Dadisi.
Dear Neighbors,
The Diamond Heights Improvements Project is finally ready to begin next week. Please review and distribute as needed the attached construction update. Inside you will find more information about the project and where we will be working next week.
Work Activity- January 30th – February 17th, 2017
Duncan St. –Carnelian St.
- Water-main installation on the westside of the street. This block will be closed to through traffic during work hours. Local access permitted. Traffic will be pushed to the eastside of the street in both directions. This work will take 1-2 weeks. Adding sidewalk, curb ramps and crosswalks along the eastside.
Arbor St. Intersection
- Adding ADA curb-ramps and crosswalk
Berkeley Way (south@ Canyon park)
- Adding sidewalk, ADA curb ramps, crosswalks and guardrails replacement at the trail entrance to Canyon Park
Diamond Heights Boulevard Pavement Renovation and Water
Main Replacement Project
SF Public Works Contract No. 2502J
SF Public Works and our contractor Hoseley Corporation are scheduled to make some major infrastructure improvements to your neighborhood. This work includes new ADA curb-ramps, sidewalk installations, new water-main installation and lastly complete roadway repaving.
Construction Schedule
Construction is scheduled to begin in January 2017 and end in January 2018. The project limits are Diamond Heights Boulevard between Portola and Sussex (12-blocks approx 2.2 miles.) The contractor will generally work one block at a time to minimize any disruptions to area residents. Since we have several locations under this contract, it may be weeks or months before we begin construction on your block. You will be notified approximately 2-weeks ahead of time with specific dates when construction begins on your block.
Work Hours
Monday through Friday: 7:00 AM – 3:00 PM.
Saturdays and Sundays: 7:00 AM – 3:00 PM. (Weekend work is not generally anticipated)
Typical Work Sequencing
Phase1 Concrete work (Curbramps, sidewalk replacement, guard-rail replacement)
Phase2 Water-line replacement
Phase 3 Roadway Repaving
Phase 4 Punch-list
Traffic Impacts
Traffic may be temporarily delayed at times as result of intersection and lane closures necessary to perform the work. “No Parking / Tow Away” signs will be posted 72 hours in advance with the project work-hours and parking restrictions.
Access to private or commercial buildings will be maintained at all times. Please observe parking and traffic signage and allow extra travel time in case of traffic delays during construction work.
We appreciate your cooperation and patience as we make improvements to your neighborhood
Dadisi Najib
Public Information Officer
Office of Communications & Public Affairs
San Francisco Public Works
City and County of San Francisco
30 Van Ness 5th Floor
San Francisco, CA 94103
Ph (415) 558-5281 Fx (415) 522-7724